2014 STP-DA Projects U5534 (I,J,K)

Milestone timeline

Bid Closing
Completed: Dec 3, 2020
December 2020
Notice to Award
Completed: Dec 18, 2020
December 2020
Notice to Proceed
Completed: Feb 1, 2021
January 2021
Construction Commences
Completed: Feb 8, 2021
February 2021
Substantial Completion
August 2021
Final Completion
September 2021
Final Project Closeout
December 2021

The projects are intended to construct a sidewalk along Old Fayetteville Road from Ricefield Branch to Leland Middle School, a multi-use path extension along Village Road from the Brunswick County Senior Center to Sturgeon Creek, and a sidewalk loop from Town Hall Drive down Village and Old Fayetteville Roads. 

AECOM

Engineering and Design

Simmons Public Utility Site Work

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Advertisement for Bids
U-5534 I, J, K

Project Updates

Leland Middle School Sidewalks
Wednesday, March 24, 2021

The contractor is installing new sidewalks in front of Leland Middle School.

Construction to Begin
Thursday, February 4, 2021

Construction on the three projects is scheduled to begin the week of February 8, 2021.  The contractor will be bringing in equipment and starting survey work.   Construction is expected to take six months to complete improvements.

Notice of Award
Friday, December 18, 2020

Town Council approved the bid and selection of Simmons Public Utility Site Work, Inc. as the construction contractor on the project.

Project Advertisement
Friday, November 6, 2020

Project is being re-advertised for construction bids.  Bid closing is slated for 2:00 pm on Thursday, December 3, 2020.