Milestone timeline

Notice To Award Bid
Completed: Jan 17, 2019
January 2019
Construction Commences
Completed: Sep 23, 2019
September 2019
Substantial Completion
Completed: Nov 22, 2019
November 2019
Final Project Closeout
Completed: May 7, 2020
February 2020

A project to construct a booster pump for the water system, in the vicinity of the existing meter vault, in order to allow the Town to better control the pressure within the system.

SEPI Engineering & Construction, Inc.

Engineering and Design

Wells Brothers Construction

Construction Contractor

Project Updates

Project Closed Out
Tuesday, March 31, 2020

Project has been officially closed out.

Preparation for Closeout
Monday, February 24, 2020

Staff has submitted Town attorney comments on the lien waiver to the contractor.  Staff is awaiting O&M manuals and the final pump report from the contractor before the final pay application is reviewed and approved for payment.

Full Pressure Test Successful
Monday, January 13, 2020

A full pressure test was conducted successfully on January 7, 2020.  SCADA monitoring equipment is currently being procured.

Additional Pump Test Scheduled
Monday, January 6, 2020

A second pump test will take place on January 7, 2020.  The construction contract will be closed out by the end of January 2020.

Final Tests for Completion are In Process
Monday, December 16, 2019

The certificate of substantial completion has been fully executed. The project team is conducting final operational tests to optimize the pump pressure settings.

Construction is Substantially Complete
Monday, December 9, 2019

Work on the construction punch list items are ongoing.