Booster Pump Project

Milestone timeline

Notice To Award Bid
Completed: Jan 17, 2019
January 2019
Construction Commences
Completed: Sep 23, 2019
September 2019
Substantial Completion
Completed: Nov 22, 2019
November 2019
Final Project Closeout
Completed: May 7, 2020
February 2020

A project to construct a booster pump for the water system, in the vicinity of the existing meter vault, in order to allow the Town to better control the pressure within the system.

SEPI Engineering & Construction, Inc.

Engineering and Design

Wells Brothers Construction

Construction Contractor

Project Updates

Booster Pump Testing is Complete
Monday, November 25, 2019

Booster pump testing has been completed.  The contractor will be completing site restoration work and electrical punch list items.

Booster Pump Testing Continues
Monday, November 18, 2019

Testing and acceptance of the booster pumps is continuing.

Booster Pumps Have Been Installed
Tuesday, November 12, 2019

The booster pumps have been installed.  Testing and acceptance is being coordinated.

Booster Pumps Have Arrived
Monday, November 4, 2019

The booster pumps arrived on November 1, 2019.  Installation is being coordinated with the contractor.

Booster Pumps Expected Delivery on November 1, 2019
Monday, October 28, 2019

The booster pumps have been shipped with an expected delivery date on Friday, November 1, 2019.

Preparatory Site Work Completion
Monday, October 14, 2019

Preparatory site work will be completed this week in anticipation of the new pump delivery.  Water service will not be interrupted for this work.