Highway 17 Sewer Expansion II Phase 1

Milestone timeline

Notice To Award Bid
Completed: Dec 10, 2019
December 2019
Construction Commences
Completed: Jan 27, 2020
January 2020
Substantial Completion
Completed: Jun 30, 2020
June 2020
Final Project Closeout
July 2020

A project to help serve the developing areas along the Highway 17 Corridor with sewer.  The project will begin at Hewett Burton Road and end at Bishops Ridge on Hazels Branch Road.  The force main will accept flows from around the area as well as additional flow from other lift stations.

WithersRavenel, Inc.

Engineering and Design

Carmichael Construction Company, Inc.

Construction Contractor

Project Updates

Force Main Installation Completed
Friday, July 10, 2020

Contractor has completed installation of the force main along Hewett Burton and Hazels Branch Road.  Next steps are for the Town and NCDOT to conduct walk through with the contractor to begin the process to close out the project.

Force Main Installation Final Stages
Tuesday, June 2, 2020

Contractor is currently working alongside Hazels Branch Road at Morgan Creek.  Project is slated for July 2020 completion.

Force Main Installation Continues Along Hazels Branch Road
Monday, May 11, 2020

Contractor is installing force main alongside the northern portion of Hazels Branch Road.

Force Main Installation Along Hazels Branch Road
Tuesday, April 7, 2020

Construction is underway. Contractor is installing force main alongside the northern portion of Hazels Branch Road.

Installation of Force Main Continues
Monday, February 24, 2020

The contractor is preparing to install the force main under Hewett Burton Road to begin the installation along Hazels Branch Road.

Dual Force Main Line Installation Complete
Monday, February 17, 2020

The contractor has completed installation of the dual force main lines from the lift station tie-in point out to the BEMC electric substation on Hewett Burton Road.