Lanvale Forest Street Improvements

Milestone timeline

Bid Closing
Completed: Aug 6, 2020
August 6, 2020
Notice to Award Bid
Completed: Aug 21, 2020
August 2020
Notice to Proceed
Completed: Sep 14, 2020
August 2020
Construction Commences
Completed: Sep 28, 2020
September 2020
Substantial Completion
Completed: Dec 31, 2020
December 2020
Final Completion
Completed: Jan 4, 2021
January 2020
Final Project Closeout
Completed: Feb 1, 2021
February 2021

A project to repair existing streets and infrastructure within the Lanvale Forest Subdivision.  The scope of the project includes repairs to existing asphalt, stormwater catch basins, sidewalks, curb and gutter, and replace existing curb ramps with ADA compliant curb ramps.

Brunswick Engineering Company

Engineering and Design

Barnhill Contracting Company

Construction Contractor

Documents

Advertisement for Bids

Project Updates

Notice of Award
Friday, August 21, 2020

Town Council approved the bid and selection of Barnhill Contracting Company as the construction contractor on the project.

Project Advertisement
Friday, July 10, 2020

Final plans and bid documents are complete.  Project is being advertisement for construction bids.  Bid closing is slated for 3:00 pm on Thursday, August 6, 2020.