Leland Police Department/Animal Control Facility

Milestone timeline

Preconstruction Design
Completed: Aug 23, 2021
August 2021
Construction Commences
January 2022
Substantial Completion
August 2022
Project Closeout
September 2022

The current Animal Control facilty is located adjacent to Founders Park in Leland, however with the redevelopment of the park in 2022, there is a need to relocate the facility.  The Town has identified a building on the new Municipal Operations Center Campus, located at 1987 Andrew Jackson Hwy NE, that once renovated, will be an ideal location for this new Animal Control facility.  In addition to Animal Control, the building will also serve as a Police evidence storage facility and house offices to support the work in both of the departments. 

Project Updates

Site Design Underway
Monday, August 23, 2021

The Town has begun prelim site design, and will be working towards a final site plan in the coming months.