Lift Station 1 Relocation (1246 Magnolia Village Way)

Milestone timeline

Bid Closing
Completed: Jun 18, 2020
June 18, 2020
Notice to Award Bid
Completed: Aug 5, 2020
August 2020
Notice to Proceed
Completed: Aug 25, 2020
August 2020
Construction Commences
Completed: Sep 21, 2020
September 2020
Substantial Completion
Completed: May 11, 2021
May 2021
Final Completion
Completed: Jun 10, 2021
June 2021
Final Project Closeout
Completed: Jun 22, 2021
June 2021

A project to reconstruct Lift Station #1 that has deteriorated and reached the end of its life cycle.

Cape Fear Engineering, Inc.

Engineering and Design

C.M. Mitchell Construction Company, Inc.

Construction Contractor

Documents

Advertisement for Bids
Old Lift Station Site
Installing New Wet Well
New Fence
New Lift Station
New Lift Station
New Lift Station Site

Project Updates

Final Walk Through Completed
Thursday, June 24, 2021

Town Staff conducted the Final Walk Through of the project with the Contractor and Engineer.  Final repairs and punch list items are complete. Town has closed out the project and transferred the site and permits to H2GO.

Old Lift Station Torn Down
Tuesday, June 1, 2021

Contractor has completed demolition of the old lift station.  Next steps are for the Town and H2GO to conduct walk through with the contractor to begin the process to close out the project.

Lift Station Startup
Wednesday, May 5, 2021

Contractor has completed the startup of the Lift Station. As-Builts are being updated for the Final Sewer Certification and the lift station will be fully operational this month. Next steps are for the contractor to demo the old lift station and bring the new lift station online.

Electrical Work
Friday, March 12, 2021

Construction continues on the new lift station.  The generator, electrical panels, and fence will be installed this month.  Brunswick Electric will be running power.  Next steps are to conduct startup of the Lift Station and complete the Final Sewer Certification before the old lift station is torn down.

Construction Continues on the Lift Station Site
Thursday, January 7, 2021

The contractor is coating the new wet well and finishing up the lift station site. Next steps are to install the electrical panels and generator.

Construction Continues
Tuesday, November 24, 2020

Construction work on the new lift station continues.  Through the month of December crews will be connecting the manholes and force main and conducting pressure testing.