Lift Station 3 Rehabilitation (8900 Timber Lane)

Milestone timeline

Informal Bid Closing
Completed: Jul 30, 2020
July 30, 2020
Notice to Award Bid
Completed: Aug 13, 2020
August 2020
Notice to Proceed
Completed: Aug 31, 2020
August 2020
Construction Commences
Completed: Sep 21, 2020
September 2020
Substantial Completion
Completed: Oct 2, 2020
September 2020
Final Completion
Completed: Oct 12, 2020
October 2020
Final Project Closeout
Completed: Oct 27, 2020
November 2020

A project to refurbish Lift Station #3 which has deteriorated due to significant sewage flow within the collection system.

Brunswick Engineering Company

Engineering and Design

Hickman Utilities, Inc.

Construction Contractor

Project Updates

Construction Complete
Tuesday, October 13, 2020

Construction work on Lift Station 3 is completed.  The Town of Leland is making final clean up and repairs to the area.  Next steps are to conduct a final inspection and close out the project.

Construction to Finish Up
Monday, October 5, 2020

Repairs to the manhole along Grandiflora Drive and Lanvale Road are complete.  The Contractor will be finishing up at the Lift Station and the by-pass pumps and temporary ramps will be removed today.

Construction Continues at Lift Station 3
Tuesday, September 29, 2020

Construction continues at Lift Station 3.  Contractors are coating the inside of the wet well and installing the pumps over the next several days.  By-pass pumps and the temporary ramp will be out a few extra days to accommodate the work.   Contractors will start repairs on the manhole along Grandiflora Drive and Lanvale Road starting Thursday, October 1st.  Repairs to the manhole should take 1 to 2 days.  Residents and visitors should expect delays as the contractor will have the Lanvale Road entrance to Magnolia Greens blocked to one-lane.

Construction to Begin
Tuesday, September 15, 2020

Construction is scheduled to begin on Monday, September 21, 2020 at the Lift Station.  The Town will be setting up by-pass pumps on Monday morning for the contractor to begin work.  There will be a temporary ramp on the golf cart pass for carts to pass over the pump.  Construction is expected to take 1-week to complete.

Project is Awarded
Thursday, August 13, 2020

The Town approved a Notice of Award to Hickman Utilities, Inc. for the Lift Station 3 Rehabilitation project.  Town Staff is finalizing contract documents and notice to proceed.  Construction to start mid September.

Proposal Due
Thursday, July 30, 2020

Design work is completed and the project is being solicited for informal bids.  Bids/proposals are due July 30, 2020.