Lift Station 3 Rehabilitation (8900 Timber Lane)

Milestone timeline

Informal Bid Closing
Completed: Jul 30, 2020
July 30, 2020
Notice to Award Bid
Completed: Aug 13, 2020
August 2020
Notice to Proceed
Completed: Aug 31, 2020
August 2020
Construction Commences
Completed: Sep 21, 2020
September 2020
Substantial Completion
September 2020
Final Completion
October 2020
Final Project Closeout
November 2020

A project to refurbish Lift Station #3 which has deteriorated due to significant sewage flow within the collection system.

Brunswick Engineering Company

Engineering and Design

Hickman Utilities, Inc.

Construction Contractor

Project Updates

Construction to Begin
Tuesday, September 15, 2020

Construction is scheduled to begin on Monday, September 21, 2020 at the Lift Station.  The Town will be setting up by-pass pumps on Monday morning for the contractor to begin work.  There will be a temporary ramp on the golf cart pass for carts to pass over the pump.  Construction is expected to take 1-week to complete.

Project is Awarded
Thursday, August 13, 2020

The Town approved a Notice of Award to Hickman Utilities, Inc. for the Lift Station 3 Rehabilitation project.  Town Staff is finalizing contract documents and notice to proceed.  Construction to start mid September.

Proposal Due
Thursday, July 30, 2020

Design work is completed and the project is being solicited for informal bids.  Bids/proposals are due July 30, 2020.