Mallory Creek Drive Patching Project

Mallory Creek Drive Patching Project

A project to repair the street in 12 locations along Mallory Creek Drive. Work shall consist of full depth asphalt replacement of all failed locations along the approximate first mile of Mallory Creek Drive from River Road SE (Highway 133), stormwater system modifications, asphalt removal, subbase removal, testing, compaction, base replacement, asphalt replacement, striping, curb and gutter replacement, adjusting water and sewer utility appurtenances to match final grade, erosion control measures and stabilization of all denuded areas, and a submitted and approved traffic control plan including installation.

SEPI Engineering & Construction, Inc.

Engineering and Design

S.T. Wooten Corporation

Construction Contractor

Project Updates

Paving Scheduled
Monday, November 18, 2019

Paving is scheduled for the section of Mallory Creek Drive between Grove Point and NC 133 for Nov. 21.

Storm Drain Near Mallory Creek Amenity Center Complete
Tuesday, November 12, 2019

The installation of the major storm drain near the Mallory Creek Amenity Center has been completed. Paving preparation work is continuing on the section between Grove Point and NC 133.

Storm Drain Replacement Underway, Paving Continues
Monday, November 04, 2019

New pavement has been placed between Tylers Cove Way and Grace Point Court. This week's work is focused on placing new pavement between Grace Point Court and NC 133, as well as completing storm drain installation in this section.

Storm Drain Replacement and Paving Planned
Monday, October 28, 2019

The contractor is working on storm drain replacement this week. Paving is also planned for the area between Tylers Cove Way and Pine Cone Drive.

Most Pavement Removal Complete, Project Continues
Monday, October 21, 2019

The contractor has completed the majority of the pavement removal work. Crews will be working this week on pavement patching between Tylers Cove Way and Pine Cone Drive. Storm drain repair work to begin this week.

Work Commences
Monday, October 14, 2019

The traffic detour has been installed and work has commenced.

Notice to Proceed
Monday, October 14, 2019

Following the pre-construction meeting with the contractor, a Notice to Proceed has been issued for Oct. 14 with the start of onsite set-up and traffic control.

Mallory Creek Drive Closed Oct. 14-Nov. 21
Thursday, October 10, 2019

Mallory Creek Drive will be closed to through traffic beginning Oct. 14 for asphalt repairs and drainage improvements along the roadway. The road will remain closed through the duration of the project, which is expected to be complete on Nov. 21. 

Traffic Management Set-up
Monday, October 07, 2019

Traffic management set-up will begin during the week of Oct. 7.

Pre-Construction Meeting
Thursday, September 26, 2019

Staff will be holding a pre-construction meeting with the contractor, S.T. Wooten.

Project Documents