Regional Pump Station 33 and Force Main Extension

Milestone timeline

Notice to Award Bid
Completed: Dec 10, 2019
December 2019
Construction Commences
Completed: Feb 6, 2020
February 2020
Substantial Completion
Completed: Jan 29, 2021
January 2021
Final Completion
March 2021
Final Project Closeout
April 2021

A project to construct a sewer lift station in Brunswick Forest to help serve the developing areas within Brunswick Forest and along the Highway 17 Corridor with sewer.  The lift station will accept additional flow from other lift stations by forcemain.  (Formerly know as the Hewett Burton Lift Station Project).

Hanover Design Services

Engineering and Design

Funston Construction Company, LLC

Construction Contractor

Project Updates

Project is Substantially Complete
Thursday, February 4, 2021

The contractor has completed the Lift Station 33 site. The Final Sewer Certification was submitted to the state and the lift station is fully operational. Next steps are for the contractor to finish punch list items and conduct a final walkthrough of the project.

Lift Station 33 Fully Operational
Thursday, January 7, 2021

Contractor has completed the Lift Station 33 site and is finishing punch list items. As-Builts are being updated for the Final Sewer Certification and the lift station will be fully operational this month. Next steps are for the Town and NCDOT to conduct a final walkthrough of the project.

Construction Work Final Stages
Tuesday, November 24, 2020

Final stages of construction work and completion of the new Lift Station are almost complete.  Next steps are for the contractor to finish punch list items and for Town to conduct a walkthrough of the project.

Final Preparations to Lift Station 33
Friday, October 23, 2020

Final Preparations are being made to the Lift Station 33 wet well.  The epoxy liner is being installed to the wet well and manholes.  Next steps are to conduct startup of the Lift Station and complete the Final Sewer Certification.

Construction to Finish Up at Lift Station 33
Monday, October 5, 2020

The force main has been installed under Highway 17 and tied in at both Ibis Landing and Hawthorne at Waterside.  The new force main is to be pressured tested and ready to go for final certification.  Stone has been put down and the fence is installed at the Lift Station site as crews prepare the wet well for its final coating.

Force Main Extended Under Highway 17
Wednesday, August 26, 2020

Contractor to start the construction to extend the force main under Highway 17 from Hawthorne at Waterside to Ibis Landing.  Contractor is also finishing up installing electrical to the lift station. 