Regional Pump Station #33 and Force Main Extension

Milestone timeline

Notice To Award Bid
Completed: Dec 10, 2019
December 2019
Construction Commences
Completed: Feb 6, 2020
February 2020
Substantial Completion
August 2020
Final Project Closeout
September2020

A project to construct a sewer lift station in Brunswick Forest to help serve the developing areas within Brunswick Forest and along the Highway 17 Corridor with sewer.  The lift station will accept additional flow from other lift stations by forcemain.  (Formerly know as the Hewett Burton Lift Station Project).

Hanover Design Services

Engineering and Design

Funston Land and Timber, LLC

Construction Contractor

Project Updates

Construction Continues on the Pump Station 33 Wet Well
Friday, July 10, 2020

Contractor is currently working on the wet well at the Pump Station 33 site. Change Order approved to extend the force main from Hawthorne at Waterside across Highway 17 to Ibis Landing.

Construction Continues on Regional Pump Station 33
Monday, May 11, 2020

Construction continues on Regional Pump Station 33. Contractor is currently working on the wet well at the Lift Station 33 site.

Force Main Installation Along Kay Todd Road
Tuesday, April 7, 2020

Construction is underway. Contractor is currently working alongside Kay Todd Road. 

Installation of Lines Complete
Monday, February 24, 2020

The contractor has completed installation of the dual forcemain lines out to Brunswick Forest Parkway as of February 17, 2020.  The contractor is working to isolate and repair an existing force main line that was damaged during the installation. 

Installation Scheduled for February 6, 2020
Monday, February 3, 2020

Installation of lines along Highway 17 is scheduled to begin on February 6, 2020.

Preconstruction Meeting Scheduled for January 30, 2020
Monday, January 20, 2020