Regional Pump Station #33 and Force Main Extension

Milestone timeline

Notice to Award Bid
Completed: Dec 10, 2019
December 2019
Construction Commences
Completed: Feb 6, 2020
February 2020
Substantial Completion
October 2020
Final Completion
November 2020
Final Project Closeout
December 2020

A project to construct a sewer lift station in Brunswick Forest to help serve the developing areas within Brunswick Forest and along the Highway 17 Corridor with sewer.  The lift station will accept additional flow from other lift stations by forcemain.  (Formerly know as the Hewett Burton Lift Station Project).

Hanover Design Services

Engineering and Design

Funston Construction Company, LLC

Construction Contractor

Project Updates

Force Main Extended Under Highway 17
Wednesday, August 26, 2020

Contractor to start the construction to extend the force main under Highway 17 from Hawthorne at Waterside to Ibis Landing.  Contractor is also finishing up installing electrical to the lift station. 

Contractor Finishing Work at the Pump Station Site
Monday, August 3, 2020

Contractor is finishing work at the Lift Station 33 site.  Electrical to be installed and final pressure testing to be completed.  Contractor is waiting on the Encroachment Agreement from NCDOT prior to extending the force main from Hawthorne at Waterside across Highway 17 to Ibis Landing.

Construction Continues on the Pump Station 33 Wet Well
Friday, July 10, 2020

Contractor is currently working on the wet well at the Pump Station 33 site. Change Order approved to extend the force main from Hawthorne at Waterside across Highway 17 to Ibis Landing.

Construction Continues on Regional Pump Station 33
Monday, May 11, 2020

Construction continues on Regional Pump Station 33. Contractor is currently working on the wet well at the Lift Station 33 site.

Force Main Installation Along Kay Todd Road
Tuesday, April 7, 2020

Construction is underway. Contractor is currently working alongside Kay Todd Road. 

Installation of Lines Complete
Monday, February 24, 2020

The contractor has completed installation of the dual forcemain lines out to Brunswick Forest Parkway as of February 17, 2020.  The contractor is working to isolate and repair an existing force main line that was damaged during the installation. 