Regional Pump Station 33 and Force Main Extension

Milestone timeline

Notice to Award Bid
Completed: Dec 10, 2019
December 2019
Construction Commences
Completed: Feb 6, 2020
February 2020
Substantial Completion
Completed: Jan 29, 2021
January 2021
Final Completion
Completed: Mar 30, 2021
March 2021
Final Project Closeout
April 2021

A project to construct a sewer lift station in Brunswick Forest to help serve the developing areas within Brunswick Forest and along the Highway 17 Corridor with sewer.  The lift station will accept additional flow from other lift stations by forcemain.  (Formerly know as the Hewett Burton Lift Station Project).

Hanover Design Services

Engineering and Design

Funston Construction Company, LLC

Construction Contractor

Project Updates

Installation Scheduled for February 6, 2020
Monday, February 3, 2020

Installation of lines along Highway 17 is scheduled to begin on February 6, 2020.

Preconstruction Meeting Scheduled for January 30, 2020
Monday, January 20, 2020
Preconstruction Conference Scheduled for the Week of January 27, 2020
Monday, January 13, 2020

The construction contract is being executed by the contractor.  A project preconstruction conference is being planned for the week of January 27, 2020.

Council Approval
Tuesday, December 10, 2019

A construction contract award was approved by Council on December 10, 2019.

Project Bid Openings
Tuesday, December 3, 2019

Bids were received and opened on December 3, 2019.