2024-2025 Town of Leland Roadway Resurfacing

Town of Leland Roadway Resurfacing 2024-2025

The Town of Leland is proposing to resurface several streets within the Town limits. The scope of the project includes milling, full depth patches as needed, asphalt overlay, new striping throughout, and new street signs as needed. The streets to be resurfaced include Carolina Avenue, Grandiflora Drive, Wyland Court, Stanfield Court, portion of Pine Harvest Drive in Magnolia Greens, Parkmore Court, Alba Lane, Tommy Jacobs Drive, Greymoss Lane, section of Westport Drive, Avebury Court, Eric Court, Potomac Court, and Sunburst Way. 

CLD Engineering, PLLC

Engineering and Design

C.M. Mitchell Construction Company, Inc.

Construction Contractor

Project Updates

Milling Continues
Thursday, September 04, 2025

Milling along Grandiflora Drive is complete, crews will now mill the side streets and head to Alba Lane, Tommy Jacobs Drive, Pine Harvest Drive, and Parkmore Court. Traffic will be diverted to one-lane and directed around the milling equipment. Residents should expect delays and use caution when driving in the area.

Milling on Grandiflora Drive
Tuesday, September 02, 2025

Milling has begun on Grandiflora Drive in Magnolia Greens.  Traffic will be diverted to one-lane.  Crews will continue on Grandiflora Drive and move to Alba Lane, Tommy Jacobs Drive, Wyland Court, Stanfield Court, Pine Harvest Drive, and Parkmore Court.  Residents should expect delays and use caution when driving in the area.

Construction to Begin
Wednesday, August 27, 2025

Construction is scheduled to begin on Tuesday, September 2, 2025. The contractor will be starting on Grandiflora Drive near Kobus Court in Magnolia Greens. First part of the work will consist of milling and full depth patches where needed. Residents should expect delays and use caution when driving in the area.

Notice of Award
Thursday, April 17, 2025

Town Council approved the bid and selection of C.M. Mitchell Construction Company as the construction contractor on the project.

Advertisement for Bids
Tuesday, February 25, 2025

The Town of Leland invites the submission of sealed construction bids for the Town of Leland Roadway Resurfacing 2024-2025 project. The bid advertisement provides complete information on the scope of work, how to obtain bidding documents, timelines, and submission requirements, and can be found at https://www.townofleland.com/rfps-rfqs. The Town will receive sealed bids for the construction of the project through Tuesday, March 25, 2025, at 3 p.m.

Final Design Plans
Friday, January 17, 2025

The Town and Engineer have finalized design plans and construction bidding documents are being drafted for advertisement and bid in Spring 2025.

Final Plans
Thursday, December 05, 2024

The Engineer has completed the Final Design Plans for the proposed resurfacing project.  Town Staff will review with the Engineer.

Preliminary Plan Review
Tuesday, September 10, 2024

Town Staff reviewed the preliminary design plans and provided comments back to the Engineer. Next steps are for the Engineer to make revisions and submit Final Design plans to the Town for review.

Preliminary Plans
Wednesday, August 28, 2024

The Engineer has completed the Preliminary Design plans for the proposed roads to be resurfaced.

Design
Monday, July 01, 2024

The Engineer has begun design on the proposed resurfacing project. Completion of the design plans is anticipated for Summer/Fall 2024.

Project Documents

Pavement Condition Assessment
Pavement Condition and Pavement Markings Condition Assessment
Pavement Condition Assessment Appendix
Pavement Condition Assessment Appendix Rating of all Town Streets