Skip to main content

Brunswick Village Boulevard & Kay Todd Utilities Extension Project

Brunswick Village Blvd & Kay Todd Utilities Extension Project

Project includes the construction of a new sewer force main, gravity sewer, and water main along Brunswick Village Boulevard Extension and Kay Todd Road. The project will help serve the developing areas within Brunswick Forest and along Kay Todd Road.

Hanover Design Services, P.A.

Engineering and Design

TBD

Construction Contractor

Project Updates

Kay Todd Road Opens
Thursday, March 25, 2021

Kay Todd Road is open to all traffic. The contractor finished installing underground utilities across Kay Todd Road and backfilled the site. There is still small cleanup needed and the contractor plans to pave early next week. Please use caution when in the area.

Kay Todd Road Closure Extended
Thursday, March 18, 2021

Due to the rain and severe weather this week, the road closure to all traffic on Kay Todd Road is being extended through 5 p.m. on March 24. All traffic will be detoured into Brunswick Forest, onto Brunswick Forest Parkway, to the water tower, and onto Kay Todd Road.

Kay Todd Road Closure
Tuesday, March 09, 2021

The Town of Leland will be closing Kay Todd Road to all traffic at 8 a.m. on March 15 and the road will remain closed until 5 p.m. on March 19. All traffic will be detoured into Brunswick Forest, onto Brunswick Forest Parkway, to the water tower, and onto Kay Todd Road.