A Project for the reconstruction of Founders Park Amphitheater.  

Samet Corporation

General Contractor

Goodrich Oaks Architecture

Architect

McGill Associates

Civil Engineer

Project Updates

Steel Erection
Friday, January 16, 2026

Over the last several weeks, crews have been reinstalling building footers and have now begun the erection of structural steel. This process will take several days, after which the focus will shift to masonry installation and the rough-in of both electrical and mechanical components.

Structure Demo and Reconstruction Beginning
Monday, December 15, 2025

The existing amphitheater structure has been deconstructed, and work is underway for the reconstruction.  The project is expected to be completed in May 2026.