Lanvale Forest Street Improvements

Milestone timeline

Bid Closing
Completed: Aug 6, 2020
August 6, 2020
Notice to Award Bid
Completed: Aug 21, 2020
August 2020
Notice to Proceed
Completed: Sep 14, 2020
August 2020
Construction Commences
Completed: Sep 28, 2020
September 2020
Substantial Completion
November 2020
Final Completion
December 2020
Final Project Closeout
January 2021

A project to repair existing streets and infrastructure within the Lanvale Forest Subdivision.  The scope of the project includes repairs to existing asphalt, stormwater catch basins, sidewalks, curb and gutter, and replace existing curb ramps with ADA compliant curb ramps.

Brunswick Engineering Company

Engineering and Design

Barnhill Contracting Company

Construction Contractor

Documents

Advertisement for Bids
Lanvale Forest Subdivision Infrastructure Advertisement

Project Updates

Concrete Work Completed
Tuesday, October 13, 2020

Construction work to repair the damaged sidewalks and curbs, repair existing curb ramps, and install new ADA compliant truncated domes is completed.  The contractor will be locating utilities over the next several weeks and then will begin repairs to the roadway.

Concrete Work Continues
Friday, October 2, 2020

Construction work to repair the damaged sidewalks and curbs, repair existing curb ramps, and install new ADA compliant truncated domes will continue through October 9th.

Construction to Begin
Tuesday, September 22, 2020

Construction is scheduled to begin on Monday, September 28, 2020.  The contractor will be bringing in equipment and starting work to repair the damaged sidewalks and curbs, repair existing curb ramps, and install new ADA compliant truncated domes.  Construction is expected to take 90-days to complete all repairs to the streets and put a new layer of asphalt down.

Town of Leland Spraying for Weeds
Friday, August 28, 2020

In preparation for the contractor to start construction on the project, the Town of Leland will be spraying for weeds over the next couple of weeks.

Notice of Award
Friday, August 21, 2020

Town Council approved the bid and selection of Barnhill Contracting Company as the construction contractor on the project.

Project Advertisement
Friday, July 10, 2020

Final plans and bid documents are complete.  Project is being advertisement for construction bids.  Bid closing is slated for 3:00 pm on Thursday, August 6, 2020.