Leland Fire Station 53

Milestone timeline

Notice to Award Bid
Completed: Sep 17, 2020
September 2020
Construction Commences
Completed: Sep 21, 2020
November 2020
Substantial Completion
November 2021
Final Project Closeout
December 2021

This project includes transforming the Town's former Municipal Operations Building at 187 Old Lanvale Road to a new Fire Station.  This project will serve the rapidly growing area along Highway 17.  The location of the new permanent, fully staffed station will aid in reducing response times to fire and life safety events in the area.  

Environments Unlimited, Inc.

Design-Build Contractor

Interior Demo
Driveway Sitework
Interior Firewall
Slab for Addition

Project Updates

Concrete slab poured for new addition
Monday, August 23, 2021

The new addition will house the sleeping rooms for the Firefighters.  Now that the slab has been poured, crews will begin framing.

Sitework has begun
Tuesday, July 6, 2021

Sitework, including clearing and tree removal, has begun.

Design/Build Amendment Executed
Friday, May 28, 2021

The Design/Build Amendment has been signed and executed with Environments Unlimited, LLC.  This is the next phase of contract documents which will allow for the building construction and sitework to proceed.  Sitework is expected to begin early June.  

Architectural and Site Plan Design
Friday, April 23, 2021

 Pre-Construction architectural and and site design plans have been approved.  Construction contract documents are being finalized and project will commence once reviewed and signed.

Notice to Proceed
Thursday, September 17, 2020

The Town issued a Notice to Proceed to Environments Unlimited, Inc. and contract documents have been signed.  Pre-Construction work will begin on September 21, 2020.

RFQ Published
Wednesday, June 24, 2020

An RFQ has been published to gather information and qualifications from interested Design-Build Firms.