A project to extend Founders Drive in the proposed Settler's Village development to Woodland Drive. The scope of the project includes constructing the roadway connection, stormwater infrastructure, five-foot sidewalk on both sides of the roadway, and installation of pavement markings and signage.

Tripp Engineering

Engineer

TCCO

Construction Contractor

Project Updates

Construction Completed
Thursday, June 18, 2026

Construction is completed on the Settler's Village Connector Road. This roadway connection improves multimodal connectivity, pedestrian access, traffic circulation, and emergency response access. It also provides an additional route for residents during severe weather or other emergency events, strengthening neighborhood connectivity and system resilience.

Punch List Items
Thursday, May 28, 2026

Final punch list items are being completed on the connector road to include installing a pedestrian crosswalk, stop bar and stop sign.

Sidewalks
Monday, February 09, 2026

DiMaio Concrete will be pouring concrete for the new sidewalks along Founders Drive.

Paving
Wednesday, January 21, 2026

Highland Paving will be installing asphalt on the new connector roadway.

Curb & Gutter
Tuesday, December 02, 2025

Curb and gutter is being installed for the roadway connection.

Construction Begins
Wednesday, October 22, 2025

Construction begins on the roadway connection to Woodland Drive.

Municipal Infrastructure Agreement
Friday, June 06, 2025

The Town entered into a Municipal Infrastructure Agreement with SV Leland, LLC for the installation of an extension of Founders Drive as a public connector street to Woodland Drive.