Leland Highway 17 Sewer Expansion II Phase 2 (Formerly Old Town Creek Lift Station Project)
Milestone timeline

A project to help serve the developing areas along the Highway 17 Corridor with sewer south of Bishops Ridge. The project will begin at Hewett Burton Road and end at Old Town Creek Road. The station on Old Town Creek Road will be designed to accept gravity sewer flow from around the area and also additional flow from other lift stations by force main.
Withers Ravenel
Engineering and Design
Civil Works Contracting
Construction Contractor
Documents
Project Updates
Construction on Old Town Creek Road is scheduled to begin the week of February 1, 2021. The contractor will be bringing in equipment and clearing and grading the new lift station site. Construction is expected to take five months to complete.
Town Council approved the bid and selection of Civil Works Contracting, LLC as the construction contractor on the project.
Final plans and bid documents are complete. Project is being advertised for construction bids. Bid closing is slated for 3:00 pm on Thursday, November 19, 2020.