Leland Highway 17 Sewer Expansion II Phase 2 (Formerly Old Town Creek Lift Station Project)

Milestone timeline

Bid Closing
Completed: Nov 19, 2020
November 19, 2020
Notice to Award Bid
Completed: Dec 18, 2020
December 2020
Notice to Proceed
Completed: Jan 11, 2021
January 2021
Construction Commences
Completed: Feb 1, 2021
February 2021
Substantial Completion
July 2021
Final Completion
August 2021
Final Project Closeout
December 2021

A project to help serve the developing areas along the Highway 17 Corridor with sewer south of Bishops Ridge.  The project will begin at Hewett Burton Road and end at Old Town Creek Road.  The station on Old Town Creek Road will be designed to accept gravity sewer flow from around the area and also additional flow from other lift stations by force main.

Withers Ravenel

Engineering and Design

Civil Works Contracting

Construction Contractor

Documents

Advertisement for Bids
Leland Highway 17 Sewer Expansion II Phase 2

Project Updates

Construction to Begin
Monday, February 1, 2021

Construction on Old Town Creek Road is scheduled to begin the week of February 1, 2021.  The contractor will be bringing in equipment and clearing and grading the new lift station site.   Construction is expected to take five months to complete.

Notice of Award
Friday, December 18, 2020

Town Council approved the bid and selection of Civil Works Contracting, LLC as the construction contractor on the project.

Project Advertisement
Wednesday, October 28, 2020

Final plans and bid documents are complete.  Project is being advertised for construction bids.  Bid closing is slated for 3:00 pm on Thursday, November 19, 2020.