Mallory Creek Drive Drainage Improvements

Mallory Creek Drive Flooding

The Town of Leland has been awarded funding through the North Carolina Resilient Coastal Communities Program (RCCP) to survey and design a grading plan to improve the frequent flooding of Mallory Creek Drive. 

CLD Engineering

Engineering and Design

Rivenbark Contracting, LLC

Construction Contractor

Project Updates

Construction Continues
Friday, April 12, 2024

Construction continues on the northside of Mallory Creek Drive from Pine Cone Drive to Blue Spruce Drive.  Construction is expected to take 2-3 weeks to complete the drainage improvements. Residents should expect delays and use caution when driving in the area.

Construction to Begin
Friday, April 05, 2024

Construction is scheduled to begin the week of April 8, 2024.  The contractor will be starting on the Pines side of Mallory Creek Drive from Pine Cone Drive to Blue Spruce Drive.  Construction is expected to take 2-3 weeks to complete the work. Residents should expect delays and use caution when driving in the area.

Construction Contractor
Friday, March 15, 2024

The Town received bids and awarded the project to Rivenbark Contracting, LLC to complete the construction of the roadside ditches.  Construction work is expected to take place in April 2024.

Project Update
Monday, December 18, 2023

The Town will be advertising and bidding the project to construct new flowing roadside ditches along Mallory Creek Drive. Construction is expected Spring 2024.

RCCP Phase 4 Grant Funding
Monday, July 24, 2023

Unfortunately, the Town of Leland was not selected for the Phase 4 Grant Funding through the North Carolina Resilient Coastal Communities Program.  The Town will look into using budgeted operational funds to complete the drianage improvements along Mallory Creek Drive.

Funding for Construction
Friday, January 20, 2023

The Town hopes to apply for RCCP Phase 4 funding to construct the roadside swales, which is anticipated to be released in April/May 2023.

Drainage Plan Completed
Tuesday, January 10, 2023

The engineer has completed the design of the drainage plan for the project area.

Survey Completed
Tuesday, October 18, 2022

The engineer has completed a survey of the project area.

Engineer
Monday, August 22, 2022

The Town has brought onboard CLD Engineering to survey the Mallory Creek Drive Drainage Improvements project.

Notice of Grant Award
Wednesday, July 13, 2022

The Town was selected for RCCP Phase 3 funding.

Project Documents

Drainage Plan
Mallory Creek Drive Drainage Improvements Drainage Plan