Northgate Drive Realignment Project

Northgate Drive Realignment Project

The project intent is for the construction of a new roadway to realign Northgate Drive, create a signalized intersection, and add and extend turn lanes on Village Road. Additional work includes the pavement of roads, utility additions, stormwater detention, a new traffic signal, and the acquisition of property for right-of-way and easements.

AECOM/URS Corporation

Engineering and Design

S.T. Wooten Corporation

Construction Contractor

Project Updates

Contractor to Begin Punch List Rework Items in December
Monday, November 25, 2019

A closeout meeting was held on Nov. 21 to discuss completion of the project punch list. The contractor will begin the punch list rework items in December.

Closeout Meeting Scheduled
Monday, November 18, 2019

A closeout meeting is scheduled with the contractor on Nov. 21 to discuss completion of the project punch list.

New Traffic Signal Fully Activated
Monday, October 14, 2019

The new traffic signal has been fully activated. A field review with NCDOT will take place on Oct. 15. Mast arm street signage is incorrect (listed as Baldwin Dr. when it should be Lee Dr.). Correct signage has been ordered and awaiting date for install.

Traffic Signal Activation
Monday, October 07, 2019

Traffic signal activation is planned during the week of Oct. 7.

Final Paving Complete
Monday, September 23, 2019

All work will be completed and open to travel by Nov. 1.

Construction Underway
Friday, September 20, 2019

Final paving and striping of Village Road improvements is expected by the end of September.