Streamflow Rehabilitation Assistance Program (StRAP)

As part of the NC Streamflow Rehabilitation Assistance Program (StRAP),  the Town was awarded a grant in the amount of $258,429 which will be used for the project. The Town has identified three streams within Town limits that have significant impairment from vegetative debris and have the potential to cause flood situations in adjacent areas.  These sections of stream total approximately 8,657 linear feet and encompass areas of Jackeys Creek, Mill Creek, and Sturgeon Creek.  The goal of this project is for vegetative debris to be cleared from the streams, and immediately adjacent areas, to restore the natural flow of water and lessen the risk of flooding. 

Alliance Integrated Solutions, Inc.

General Contractor

Project Updates

All Grant Reimbursements Received
Friday, April 28, 2023

The Town has received 100% reimbursement on the project and is currently awaiting project closeout.  

Debris Removal Complete
Friday, March 10, 2023

Crews have completed all work associated with debris removal and have hauled off over 12 tons of vegetative debris from locations in and adjacent to streams.

Work has started
Friday, January 20, 2023

Work has began on removing vegetative debris.  Crews have mobilized to areas adjacent to Jackeys Creek and will complete this section before moving to the other areas.

Mobilization expected by mid-December
Wednesday, November 30, 2022

A project kick-off meeting was held in November and construction crews are expected to mobilize by mid-December to begin work on the project.  

Contract Executed
Wednesday, October 26, 2022

A construction contract has been signed and executed with Alliance Integrated Solutions, Inc. for the project.  Work is expected to begin in December 2022.