Brunswick Forest Parkway & Low Country Blvd Intersection Improvements

Milestone timeline

Bid Closing
Completed: Mar 25, 2021
March 25, 2021
Notice to Award Bid
Completed: Apr 16, 2021
April 2021
Notice to Proceed
Completed: May 3, 2021
May 2021
Construction Commences
Completed: Sep 7, 2021
September 2021
Substantial Completion
Completed: Sep 28, 2021
September 2021
Final Completion
Completed: Nov 2, 2021
November 2021
Final Project Closeout
January 2022

A project to improve the intersection at Brunswick Forest Parkway and Low Country Boulevard.  The scope of the project includes restriping Brunswick Forest Parkway and Low Country Boulevard and installing a single-lane roundabout at the intersection.

C.M. Mitchell Construction Company, Inc.

Construction Contractor

Kittelson & Associates, Inc.

Engineering and Design

Documents

Project Information
Project Information Sheet for Brunswick Forest Parkway & Low Country Blvd Intersection Improvements
Construction Plans
Construction Plans for Brunswick Forest Parkway & Low Country Blvd Intersection Improvements
Roundabout Information
FHWA Roundabout Safety Brochure
Brunswick Forest
Brunswick Forest Parkway
Brunswick Forest Parkway
Brunswick Forest Parkway Lane Closure
Demo of Concrete Island
Demo of Concrete Island
Demo of Concrete Island
New Concrete Island
New Concrete Island
Stamped Concrete Island

Pages

Project Updates

Yield Ahead Striping Delayed
Monday, January 17, 2022

Due to the colder temperatures today, the installation of the Yield Ahead Striping at the Brunswick Forest Parkway and Low Country Blvd roundabout has been pushed to this Wednesday and Thursday, January 19-20, 2022.  Work to install the striping will take two-days to complete and will require lane closures while crews work in the travel lane.  Vehicles will be directed around the area that crews will be in.  Please use caution when driving in the area.

Yield Ahead Striping Update
Thursday, January 6, 2022

Due to weather and the colder temperatures predicted for next week, Town of Leland Streets Department is delaying the installation of the Yield Ahead Striping at the Brunswick Forest Parkway and Low Country Blvd roundabout to January 18-19, 2022.  Work to install the striping will take two-days to complete, and will require lane closures while crews work in the travel lane.  Vehicles will be directed around the area that crews will be in.  Please use caution when driving in the area.

Yield Ahead Striping
Monday, January 3, 2022

The Town of Leland Streets Department will be installing Yield Ahead Striping at the Brunswick Forest Parkway and Low Country Blvd roundabout starting next Monday, January 10, 2022.  Work will take two-days to complete, weather permitting, and will require lane closures while crews work in the travel lane.  Vehicles will be directed around the area that crews will be in.  Please use caution when driving in the area.

Project Complete
Thursday, November 4, 2021

The contractor has completed the construction of the single-lane roundabout at Brunswick Forest Parkway and Low Country Boulevard and the intersection is open to traffic. Town Staff is working with the Engineer to close out the project.

Additional Striping
Monday, November 1, 2021

The Town of Leland will be installing a solid yellow stripe around the concrete island for the single-lane roundabout at Brunswick Forest Parkway and Low Country Blvd.  This will aid in the visibility of the island.  Crews will be out tomorrow, Tuesday, November 2, 2021.  Work should take a few hours to complete, and the roundabout will remain open to traffic.  Please use caution when driving in the area.

Final Walk Through Completed
Friday, October 1, 2021

Town Staff conducted the Final Walk Through of the project with the Engineer and Contractor. Final adjustments and punch list items will be completed today and Monday, October 4, 2021. The Brunswick Forest Wellness Center entrance will be opened later this afternoon. Town Staff will continue to monitor the area.