Brunswick Forest Parkway & Low Country Blvd Intersection Improvements

Milestone timeline

Bid Closing
Completed: Mar 25, 2021
March 25, 2021
Notice to Award Bid
Completed: Apr 16, 2021
April 2021
Notice to Proceed
Completed: May 3, 2021
May 2021
Construction Commences
August 2021
Substantial Completion
September 2021
Final Completion
October 2021
Final Project Closeout
November 2021

A project to improve the intersection at Brunswick Forest Parkway and Low Country Boulevard.  The scope of the project includes restriping Brunswick Forest Parkway and Low Country Boulevard and installing a roundabout at the intersection. 

C.M. Mitchell Construction Company, Inc.

Construction Contractor

Kittelson & Associates, Inc.

Engineering and Design

Documents

Advertisement for Bids
Construction Plans
Construction Plans for Brunswick Forest Parkway & Low Country Blvd Intersection Improvements
Project Information
Project Information Sheet for Brunswick Forest Parkway & Low Country Blvd Intersection Improvements
Brunswick Forest
Brunswick Forest Parkway
Brunswick Forest Parkway

Project Updates

Construction Delayed
Thursday, May 20, 2021

Construction on the Brunswick Forest Parkway and Low Country Blvd is delayed due to manufacturing delays with the signposts and curbing. To minimize disruptions and impacts to the community, the contractor is going to wait until all materials are received before starting construction. Construction is scheduled to begin end of August/early September 2021.

Construction to Begin
Wednesday, May 5, 2021

Construction is scheduled to begin June 2021.

Notice of Award
Thursday, April 15, 2021

Town Council approved the bid and selection of C.M. Mitchell Construction Company as the construction contractor on the project.

Project Advertisement
Tuesday, March 9, 2021

Final plans and bid documents are complete.  Project is being advertisement for construction bids.  Bid closing is slated for 3:00 pm on Thursday, March 25, 2021.

Traffic Monitoring Plan
Wednesday, October 14, 2020

Kittelson & Associates completed the Traffic Monitoring Plan for the project.  A single-lane roundabout was found to meet capacity of the intersection.

Engineering Firm Selected
Tuesday, September 1, 2020

Town signed contract with Kittelson & Associates to complete the Traffic Monitoring Plan and design for the intersection improvements.