Milestone timeline

Bid Closing
January 28, 2021
Notice to Award Bid
February 19, 2021
Notice to Proceed
March 2021
Construction Commences
March 2021
Substantial Completion
May 2021
Final Completion
June 2021
Final Project Closeout
July 2021

A project to improve the intersection at Brunswick Forest Parkway and Low Country Boulevard.  The scope of the project includes restriping existing thermostriping along Brunswick Forest Parkway and Low Country Boulevard and install a roundabout at the intersection. 

Kittelson & Associates, Inc.

Engineering and Design

TBD

Construction Contractor

Documents

Advertisement for Bids
Brunswick Forest Parkway and Low Country Boulevard Intersection Improvements

Project Updates

Project Advertisement
Thursday, January 7, 2021

Final plans and bid documents are complete.  Project is being advertisement for construction bids.  Bid closing is slated for 3:00 pm on Thursday, January 28, 2021.