Skip to main content

Sturgeon Creek Park

Sturgeon Creek Aerial

The currently undeveloped Sturgeon Creek Park is intended to serve as Leland’s second water access park. With more than 78 acres, this park has the potential to become a destination facility both locally and regionally for sportsmen and water lovers wishing to gain access to Sturgeon Creek and the Brunswick River. Sitting on Sturgeon Creek, the focus for this facility will be boating access from an NC Fish and Wildlife boat ramp as well as environmental education, preservation, and nature-based activities. Town Council adopted the Master Plan at its Feb. 2020 regular meeting. Next steps for the project will be to move forward with engineering when additional funding is available.

North Carolina Wildlife Resources Commission

Boat Ramp Design & Construction 

Withers Ravenel

Engineering Firm-Environmental Consultant

Project Updates

Brownfields Property Progress
Tuesday, December 23, 2025

The Town has continued working with NCDEQ to complete tasks associated with designating several parcels as Brownfields properties. These parcels were formerly home to a junkyard, and environmental testing and reporting have been completed to support the Brownfields designation and help define future use of the sites.

Boat Ramp Design
Tuesday, December 23, 2025

The Town continues to work with NCWRC on the design of the future boat ramp. Due to staffing changes within NCWRC, progress has been slower than originally anticipated; however, the Town remains optimistic that significant progress toward completing design and permitting will occur in 2026.

Permitting Process to Begin
Tuesday, January 21, 2025

WRC has provided another round of proposed design for the future boat ramp.  As the Town works through approval of the design, WRC will be starting the pre-construction permitting process.  

Boat Ramp Design
Tuesday, July 23, 2024

With the boat ramp preliminary, concept design completed, next steps for the project will involve holding a scoping meeting with CAMA and other stakeholders to get approval to continue with design.  This meeting is expected to happen within the next 2 months, however an official date has not yet been determined.

Underground Storage Tank Investigation
Thursday, June 27, 2024

Through environmental testing, there were several areas of the site identified as possibly having underground storage tanks, which would need removal.  The Town has completed investigation of these areas and confirmed that there were no underground tanks present.  

Prelim Boat Ramp Plans
Wednesday, June 05, 2024

The Town has received preliminary site plans for the construction of a NC Wildlife Resource Commission boat ramp, which will be Phase 1 of the overall park project.  Next steps include holding a scoping meeting with WRC, CAMA, and other stakeholders to determine is the proposed plan will meet all requirements necessary to move forward with the design and future construction.  

Environmental Testing Completed
Monday, April 01, 2024

As part of the Brownfields Program, environmental testing was required for multiple parcels in the future Sturgeon Creek Park.  Testing has been completed and NCDEQ is currently working on a final Brownfields report which establishes as future work plan that must be adhered to in regard to future development. 

Environmental Testing Reports Received
Thursday, February 29, 2024

The Town has received reports relating to enviromental testing as part of the ongoing Brownfields program.  We are expecting to receive the completed Brownfields report by July 2024 and will coincide with the design of the public boat ramp by NC Wildlife.

Town has received grant funding for completion of Brownfields Study
Friday, September 01, 2023

The Town has partnered with NCDENR and EPA to secure grant funding for the completion of the Brownfields Study.  This funding includes environmental field testing and administrative work associated with completing the Brownfields agreement.  Testing is currently in progress.

NCDENR Project Manager Assigned for Brownfields Study
Friday, April 28, 2023

The Town has been assigned a project manager through NCDEQ to begin work on the Brownfields Study.  This PM will work closely with the Town, as well as, the Town's contracted engineer to develop a workplan to address environmental concerns on the property.  This process is expected to take at least a year to complete and gain full approval.