Leland Police Department Animal Control Facility

Milestone timeline

Preconstruction Design
Completed: Aug 23, 2021
August 2021
Construction Commences
Completed: Apr 25, 2022
April 2022
Substantial Completion
August 2022
Project Closeout
September 2022

The current Animal Control facilty is located adjacent to Founders Park in Leland, however with the redevelopment of the park in 2023, there is a need to relocate the facility.  The Town has identified a building on the new Municipal Operations Center Campus, located at 1987 Andrew Jackson Hwy NE, that once renovated, will be an ideal location for this new Animal Control facility. 

Environments Unlimited, Inc.

General Contractor

Documents

Cut for Trench Drain

Project Updates

Start of Construction
Monday, April 25, 2022

Construction has begun on the new Animal Control facility.  This is a renovation/redesign of a current building that is on the Municipal Operations Center Campus.   

Obtaining Quotes for Renovation Work
Tuesday, February 22, 2022

The Town has obtained quotes for the interior renovation work and will soon be selecting a contractor to perform the work.  Renovations are expected to begin by April 2022.

Prelim Architectural Design has begun
Monday, November 1, 2021

Prelim architectural design has begun and is being incorporated into the prelim site plan.

Site Design Underway
Monday, August 23, 2021

The Town has begun prelim site design, and will be working towards a final site plan in the coming months.