Mallory Creek Drive Patching Project

Milestone timeline

Notice To Award Bid
Completed: Jul 18, 2019
July 2019
Construction Commences
Completed: Oct 14, 2019
October 2019
Substantial Completion
Completed: Dec 18, 2019
December 2019
Final Project Closeout
July 2020

A project to repair the street in 12 locations along Mallory Creek Drive. Work shall consist of full depth asphalt replacement of all failed locations along the approximate first mile of Mallory Creek Drive from River Road SE (Highway 133), stormwater system modifications, asphalt removal, subbase removal, testing, compaction, base replacement, asphalt replacement, striping, curb and gutter replacement, adjusting water and sewer utility appurtenances to match final grade, erosion control measures and stabilization of all denuded areas, and a submitted and approved traffic control plan including installation.

SEPI Engineering & Construction, Inc.

Engineering and Design

S.T. Wooten Corporation

Construction Contractor

Documents

Detour Map
Detour Map
Bid Award Letter
Bid Letter
Mallory Creek Road Closure
Notice of Temporary Road Closure
Project Map

Project Updates

Final Repairs Completed
Monday, May 11, 2020

Contractor completed final repairs.  Town is working with Engineering Firm and Contractor on warranty items to close out the project.

Final Repairs
Tuesday, April 7, 2020

Contractor is completing final repairs and punch list items.  Town is working with Engineering Firm and Contractor on warranty items.

Preparation for Final Closeout in March 2020
Monday, February 24, 2020

A meeting is scheduled this week to finalize the contractor's repair plans and the material testing error issues.  The remaining repair work is planned to be completed by mid-March 2020.

Updated Closeout Scheduled for February 2020
Monday, February 10, 2020

Staff met with the contractor and HOA representatives on February 3, 2020 to review irrigation and electrical items that were damaged during the project.  The HOA landscape vendor has provided a repair proposal to the contractor for the assessment of these items, and staff will continue to monitor the progress for satisfactory resolution.

Construction Closeout Scheduled for January 2020
Monday, January 27, 2020

All construction work was substantially completed on December 18, 2019.   The contractor is working to repair damaged irrigation and electrical items.  A field review was held on January 27, 2020.  The construction contract will be closed out by January 31, 2020.

Pavement Marking of the Roads Has Commenced
Monday, December 16, 2019

Pavement marking began on December 16, 2019 with substantial completion of the project to occur by December 20, 2019.