Skip to main content

Mallory Creek Drive Patching Project

Mallory Creek Drive Patching Project

A project to repair the street in 12 locations along Mallory Creek Drive. Work shall consist of full depth asphalt replacement of all failed locations along the approximate first mile of Mallory Creek Drive from River Road SE (Highway 133), stormwater system modifications, asphalt removal, subbase removal, testing, compaction, base replacement, asphalt replacement, striping, curb and gutter replacement, adjusting water and sewer utility appurtenances to match final grade, erosion control measures and stabilization of all denuded areas, and a submitted and approved traffic control plan including installation.

SEPI Engineering & Construction, Inc.

Engineering and Design

S.T. Wooten Corporation

Construction Contractor

Project Updates

Final Repairs Completed
Monday, May 11, 2020

Contractor completed final repairs. Town is working with engineering firm and contractor on warranty items to close out the project.

Final Repairs
Tuesday, April 07, 2020

Contractor is completing final repairs and punch list items. Town is working with engineering firm and contractor on warranty items.

Preparation for Final Closeout in March 2020
Monday, February 24, 2020

A meeting is scheduled this week to finalize the contractor's repair plans and the material testing error issues. The remaining repair work is planned to be completed by mid-March 2020.

Updated Closeout Scheduled for Feb. 2020
Monday, February 10, 2020

Staff met with the contractor and HOA representatives on Feb. 3 to review irrigation and electrical items that were damaged during the project. The HOA landscape vendor has provided a repair proposal to the contractor for the assessment of these items, and staff will continue to monitor the progress for satisfactory resolution.

Construction Closeout Scheduled for Jan. 2020
Monday, January 27, 2020

All construction work was substantially completed on Dec. 18. The contractor is working to repair damaged irrigation and electrical items. A field review was held on Jan. 27. The construction contract will be closed out by Jan. 31.

Pavement Marking of Roads has Commenced
Monday, December 16, 2019

Pavement marking began on Dec. 16 with substantial completion of the project to occur by Dec. 20.

Paving Complete
Friday, December 13, 2019

Paving has been completed. Pavement marking is scheduled to begin on Dec. 16, with final work being completed by the end of next week.

Project Completion Expected this Month
Monday, December 09, 2019

Repairs between Tylers Cove Way and North Palm Drive is ongoing. Paving for this section is planned for mid-week. The remainder of the road patching from North Palm Drive to Pine Cone Drive will begin late this week. Overall project completion is expected this month.

Detour Removed
Monday, December 02, 2019

Paving is complete for the section between Tylers Cove Way and NC 133. The detour was removed on Nov. 27. Repairs between Tylers Cove Way and North Palm Drive have begun with one lane traffic and flaggers monitoring traffic flows.

Detour to be Removed by Nov. 27
Monday, November 25, 2019

Paving has been completed for the section between Tylers Cove Way and NC 133. The detour will be removed by Nov. 27. Repairs between Tylers Cove Way and North Palm Drive will begin on Dec. 2 with one lane traffic and flaggers.

Project Documents