Northgate Drive Realignment Project

Milestone timeline

Notice To Award Bid
Completed: Nov 30, 2017
November 2017
Construction Commences
Completed: Apr 1, 2018
April 2018
Substantial Completion
Completed: Nov 21, 2019
November 2019
Final Project Closeout
July 2020

The project intent is for the construction of a new roadway to realign Northgate Drive, create a signalized intersection, and add and extend turn lanes on Village Road.  Additional work to include the pavement of roads, utility additions, stormwater detention, a new traffic signal, and the acquisition of property for right of way and easements.

AECOM/URS Corporation

Engineering and Design

S.T. Wooten Corporation

Construction Contractor

Project Updates

Final Repairs
Monday, May 11, 2020

Contractor is completing final repairs and punch list items.  Town is working with Engineering Firm and Contractor on closing out the project.

Final Repairs
Tuesday, April 7, 2020

Additional design work was needed for repairs.  NCDOT approved work.  Next steps are to schedule Contractor to complete repairs.

Repair Work Scheduled to be Completed by April 1, 2020
Monday, February 24, 2020

A field review meeting is scheduled this week with the contractor.  Repair work will be scheduled with an estimated completion date of April 1, 2020.

Final Closeout Preparation Meetings Scheduled
Monday, February 17, 2020

Staff and the contractor are meeting on February 20, 2020 to finalize the repair plan in preparation for a meeting with NCDOT during the week of February 24, 2020.

Updated Final Closeout Scheduled for February 2020
Monday, February 10, 2020

Staff and the contract engineer are reviewing a fourth repair proposal from the designer, and if deemed feasible by the contractor, it will be submitted to NCDOT for approval and subsequent construction by the contractor.

Final Project Review to Occur by January 31, 2020
Tuesday, January 21, 2020

Survey data needed to facilitate repair design was completed on January 3, 2020.  Staff met with the original designer and the contractor on January 10, 2020 to further discuss repair options and are currently awaiting an update from the designer on the status of the repair plan.  The final repair design is expected to be completed and reviewed with NCDOT by January 31, 2020.