Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

Milestone timeline

Bid Closing
Completed: Aug 27, 2020
August 2020
Notice to Award
Completed: Sep 17, 2020
September 2020
Notice to Proceed
Completed: Oct 13, 2020
October 2020
Construction Commences
Completed: Oct 26, 2020
October 2020
Substantial Completion
June 2021
Final Completion
July 2021
Final Project Closeout
December 2021

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School.  Project also includes the repaving of Old Fayetteville Road.  Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Paper
Project Information Paper

Project Updates

Construction to Begin
Thursday, October 22, 2020

Construction on Old Fayetteville Road is scheduled to begin the week of October 26, 2020.  The contractor will be bringing in equipment and starting survey work.   Construction is expected to take nine months to complete improvements.

Notice of Award
Thursday, September 17, 2020

Town Council approved the bid and selection of C.M. Mitchell Construction Company as the construction contractor on the project.