Milestone timeline

Bid Closing
Completed: Aug 27, 2020
August 2020
Notice to Award
Completed: Sep 17, 2020
September 2020
Notice to Proceed
Completed: Oct 13, 2020
October 2020
Construction Commences
Completed: Oct 26, 2020
October 2020
Substantial Completion
August 2021
Final Completion
September 2021
Final Project Closeout
December 2021

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School.  Project also includes the repaving of Old Fayetteville Road.  Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Project Information Paper

Project Updates

Old Fayetteville Road Extended Lane Closure
Friday, April 16, 2021

The Town of Leland will have an extended lane closure on Old Fayetteville Road Monday, April 19, 2021 from 8:00 am to 7:00 pm for the contractor to pave the shoulder of the road.  Work will require one lane to be closed with flagging for the duration.  Residents will still be able to access their homes/property during paving operations. 

Old Fayetteville Road Extended Lane Closure
Tuesday, March 16, 2021

The Town of Leland will have an extended lane closure on Old Fayetteville Road tomorrow, March 17, 2021 from 8:00 am to 6:00 pm for the contractor to connect to H2GO’s waterline. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during the utility work.

Installation of Curb and Gutter
Thursday, January 7, 2021

The contractor is continuing to lay storm drainpipe and next steps are to install concrete for the curb and gutter along Old Fayetteville Road.

Widening of Old Fayetteville Road
Friday, December 18, 2020

The contractor will be widening Old Fayetteville Road and plans to lay asphalt starting on Monday.  Work will consist of grading, paving, and installing curb and gutter along Old Fayetteville Road.

Construction to Begin
Thursday, October 22, 2020

Construction on Old Fayetteville Road is scheduled to begin the week of October 26, 2020.  The contractor will be bringing in equipment and starting survey work.   Construction is expected to take nine months to complete improvements.

Notice of Award
Thursday, September 17, 2020

Town Council approved the bid and selection of C.M. Mitchell Construction Company as the construction contractor on the project.