Skip to main content

Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School. Project also includes the repaving of Old Fayetteville Road. Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Administration & Construction Engineering Inspection Services

Project Updates

NCDOT Mobi Awards Finalist
Tuesday, April 26, 2022

The U-5534 D Old Fayetteville Road Multi-Use Path and Resurfacing project was named one of 12 finalists for the 2022 NCDOT Mobi Awards. The intent of NCDOT’s Mobi Awards is to recognize completed multimodal projects throughout North Carolina that contribute to creating safe, connected, and livable communities. This year’s winner and honorable mentions will be recognized on May 4.

NCDOT Mobi Awards
Monday, February 14, 2022

The U-5534 D Old Fayetteville Road Multi-Use Path and Resurfacing project has been nominated for the 2022 NCDOT Mobi Awards. The intent of NCDOT’s Mobi Awards is to recognize completed multimodal projects throughout North Carolina that contribute to creating safe, connected, and livable communities. Judges will select finalists for five categories that are rural, small urban, urban, large urban, and innovation. A sixth category, most voted project, will be determined by votes from the public. Individuals are eligible to vote up to three times daily for their favorite project(s). Voting is open online through Feb. 25.

Finalists in each of the six categories will be notified in March and winners announced on May 4.

Construction Complete
Friday, December 03, 2021

Construction is complete on the Old Fayetteville Road Improvements and Multi-Use Path. Town staff is working with NCDOT to close out the project.

Final Walk-Through Completed
Thursday, November 04, 2021

Town staff and NCDOT conducted the final walk-through of the project with the engineer and contractor. Final punch list items are being worked on and expected to be completed in the coming weeks. Town staff will continue to monitor the area and work with NCDOT to close out the project.

Ribbon Cutting
Monday, October 18, 2021

Thank you to all who joined the Town for the opening of the multi-use path. Big thanks to NCDOT and the WMPO for their collaboration with this project. The Town is excited to have this contribution to the community.

Punch List Items Remain
Wednesday, October 06, 2021

The Town’s construction engineer has completed the initial walk-through of the project. The next steps are for the contractor to complete punch list items and clean up the project site. A ribbon cutting ceremony is scheduled for Oct. 18 at 12 p.m.

Striping Complete
Friday, August 13, 2021

Striping on Old Fayetteville Road is complete. The contractor will be putting final touches on the project to include installing new street signs and ADA mats, putting down seed and straw, and cleaning up the project site.

Striping Old Fayetteville Road
Tuesday, August 10, 2021

Thermoplastic striping will be installed on Old Fayetteville Road on Aug. 11 and 12. During this time, expect delays. Work will require one lane to be closed with flagging for the duration and will move down the road while the paint truck is rolling through.

Paving Complete
Friday, July 30, 2021

Paving on Old Fayetteville Road and for the multi-use path is now complete. The next steps are for the contractor to install thermoplastic striping, back fill the shoulders, and install concrete curb ramps and new mailboxes in the weeks to come. Work will require one lane to be closed with flagging for the duration.

Paving Continues
Friday, July 23, 2021

Paving operations along Old Fayetteville Road will continue July 23-30. During this time, the contractor will have an extended lane closure on Old Fayetteville Road from 8 a.m. to 7 p.m. to pave the multi-use path and put down the final asphalt for the road. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during paving operations.

Project Documents

Project Information Sheet
Old Fayetteville Road Improvements Project Details