Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

Milestone timeline

Bid Closing
Completed: Aug 27, 2020
August 2020
Notice to Award
Completed: Sep 17, 2020
September 2020
Notice to Proceed
Completed: Oct 13, 2020
October 2020
Construction Commences
Completed: Oct 26, 2020
October 2020
Substantial Completion
Completed: Aug 12, 2021
September 2021
Final Completion
Completed: Nov 8, 2021
November 2021
Final Project Closeout
April 2022

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School.  Project also includes the repaving of Old Fayetteville Road.  Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Old Fayetteville Road Improvements Project Details
Multi-Use Path
Multi-Use Path
Multi-Use Path
Multi-Use Path
Striping on Old Fayetteville Road
Striping on Old Fayetteville Road
Final Paving on Old Fayetteville Road
Paving Multi-Use Path
Paving Old Fayetteville Road
Grading for Multi-Use Path

Pages

Project Updates

Multi-Use Path Wins NCDOT Mobi Award
Thursday, May 5, 2022

The Town of Leland is proud to announce the Old Fayetteville Road Multi-Use Path and Resurfacing project has won a 2022 N.C. Department of Transportation Mobi Award.

The Old Fayetteville Road Multi-Use Path was one of 12 finalists and named the winner on May 4. The project won in the small urban category, which recognizes small-to-medium communities or counties with population between 10,000 and 50,000.

NCDOT Mobi Awards Finalist
Tuesday, April 26, 2022

The U-5534 D Old Fayetteville Road Multi-Use Path and Resurfacing project named one of 12 finalist for the 2022 NCDOT Mobi Awards Finalist.  The intent of NCDOT’s Mobi Awards is to recognize completed multimodal projects throughout North Carolina that contribute to creating safe, connected, and livable communities.  This year’s winner and honorable mentions will be recognized on May 4, 2022.

https://www.townofleland.com/news/old-fayetteville-road-multi-use-path-named-ncdot-mobi-awards-finalist

 

NCDOT Mobi Awards
Monday, February 14, 2022

The U-5534 D Old Fayetteville Road Multi-Use Path and Resurfacing project has been nominated for the 2022 NCDOT Mobi Awards.  The intent of NCDOT’s Mobi Awards is to recognize completed multimodal projects throughout North Carolina that contribute to creating safe, connected, and livable communities.  Judges will select finalists for five categories that are Rural, Small Urban, Urban, Large Urban, and Innovation.  A sixth category, Most Voted Project, will be determined by votes from the public.  Individuals are eligible to vote up to three times daily for their favorite project(s).  Voting is open through February 25, 2022.

https://ncdot.submittable.com/gallery/58654547-8b8f-4d2a-834c-054559fdd001

Finalists in each of the six categories will be notified in March and winners announced on May 4, 2022.

 

Construction is Complete
Friday, December 3, 2021

Construction is complete on the Old Fayetteville Road Improvements and Multi-Use Path.  Town Staff is working with NCDOT to close out the project.

Final Walk Through Completed
Thursday, November 4, 2021

Town Staff and NCDOT conducted the Final Walk Through of the project with the Engineer and contractor.  Final punch list items are being worked on and expected to be completed in the coming weeks.  Town Staff will continue to monitor the area and will work with NCDOT to close out the project.

Ribbon Cutting
Monday, October 18, 2021

Thank you to all who joined the Town in the opening of the multi-use path. Big thanks to NCDOT and the WMPO for their collaboration with this project. The Town is excited to have this contribution to the community.