Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

Milestone timeline

Bid Closing
Completed: Aug 27, 2020
August 2020
Notice to Award
Completed: Sep 17, 2020
September 2020
Notice to Proceed
Completed: Oct 13, 2020
October 2020
Construction Commences
Completed: Oct 26, 2020
October 2020
Substantial Completion
September 2021
Final Completion
October 2021
Final Project Closeout
December 2021

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School.  Project also includes the repaving of Old Fayetteville Road.  Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Old Fayetteville Road Improvements Project Details
Construction Plans
Old Fayetteville Road
Construction Commences
Work near Basin Street
Grading for Multi-Use Path
Paving Old Fayetteville Road
Paving Multi-Use Path

Project Updates

Paving Continues
Friday, July 23, 2021

Paving operations along Old Fayetteville Road will continue today, Friday, July 23 through July 30. During this time, the contractor will have an extended lane closure on Old Fayetteville Road from 8:00 am to 7:00 pm to pave the Multi-Use Path and put down the final asphalt for the road. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during paving operations.

Paving Multi-Use Path
Wednesday, July 7, 2021

The contractor will be paving the curb line along Old Fayetteville Road and Multi-Use Path starting this week. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during paving operations.

Construction Continues on the Multi-Use Path
Thursday, June 24, 2021

The contractor is installing concrete for the curb and gutter along Old Fayetteville Road and anticipates paving the Multi-Use Path in July.

Construction Continues
Wednesday, May 5, 2021

The contractor is continuing to lay storm drainpipe and installing concrete for the curb and gutter along Old Fayetteville Road.

Old Fayetteville Road Extended Lane Closure
Friday, April 16, 2021

The Town of Leland will have an extended lane closure on Old Fayetteville Road Monday, April 19, 2021 from 8:00 am to 7:00 pm for the contractor to pave the shoulder of the road.  Work will require one lane to be closed with flagging for the duration.  Residents will still be able to access their homes/property during paving operations. 

Old Fayetteville Road Extended Lane Closure
Tuesday, March 16, 2021

The Town of Leland will have an extended lane closure on Old Fayetteville Road tomorrow, March 17, 2021 from 8:00 am to 6:00 pm for the contractor to connect to H2GO’s waterline. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during the utility work.