Old Fayetteville Road Multi-Use Path (STP-DA U-5534D)

Milestone timeline

Bid Closing
Completed: Aug 27, 2020
August 2020
Notice to Award
Completed: Sep 17, 2020
September 2020
Notice to Proceed
Completed: Oct 13, 2020
October 2020
Construction Commences
Completed: Oct 26, 2020
October 2020
Substantial Completion
Completed: Aug 12, 2021
September 2021
Final Completion
October 2021
Final Project Closeout
December 2021

A project to develop a roadside multi-use path along the north side of Old Fayetteville Road from Town Hall Drive to North Brunswick High School.  Project also includes the repaving of Old Fayetteville Road.  Work will require brief lane closures with flagging for duration.

AECOM

Engineering and Design

C.M. Mitchell Construction Company

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Old Fayetteville Road Improvements Project Details
Old Fayetteville Road
Construction Commences
Work near Basin Street
Grading for Multi-Use Path
Paving Old Fayetteville Road
Paving Multi-Use Path
Final Paving on Old Fayetteville Road
Striping on Old Fayetteville Road
Striping on Old Fayetteville Road

Project Updates

Punch List Items Remain
Wednesday, October 6, 2021

The Town’s Construction Engineer has completed the initial walk through of the project. The next steps are for the contractor to complete punch list items and clean up the project site. A ribbon cutting ceremony is scheduled for October 18, 2021 at noon.

Striping Complete
Friday, August 13, 2021

Striping on Old Fayetteville Road is complete. The contractor will be putting final touches on the project to include installing new street signs and ADA mats, putting down seed and straw, and cleaning up the project site.

Striping Old Fayetteville Road
Tuesday, August 10, 2021

Thermoplastic striping will be installed on Old Fayetteville Road this Wednesday and Thursday, August 11-12, 2021. During this time, please expect delays. Work will require one lane to be closed with flagging for the duration and will move down the road while the paint truck is rolling through.

Paving Complete
Friday, July 30, 2021

Paving on Old Fayetteville Road and for the Multi-Use Path is now complete. The next steps are for the contractor to install thermoplastic striping, back fill the shoulders, install concrete curb ramps and new mailboxes in the weeks to come. Work will require one lane to be closed with flagging for the duration.

Paving Continues
Friday, July 23, 2021

Paving operations along Old Fayetteville Road will continue today, Friday, July 23 through July 30. During this time, the contractor will have an extended lane closure on Old Fayetteville Road from 8:00 am to 7:00 pm to pave the Multi-Use Path and put down the final asphalt for the road. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during paving operations.

Paving Multi-Use Path
Wednesday, July 7, 2021

The contractor will be paving the curb line along Old Fayetteville Road and Multi-Use Path starting this week. Work will require one lane to be closed with flagging for the duration. Residents will still be able to access their homes/property during paving operations.

Pages