STP-DA Pedestrian Improvements (U-5534I, J, K)

Milestone timeline

Bid Closing
Completed: Dec 3, 2020
December 2020
Notice to Award
Completed: Dec 18, 2020
December 2020
Notice to Proceed
Completed: Feb 1, 2021
January 2021
Construction Commences
Completed: Feb 8, 2021
February 2021
Substantial Completion
August 2021
Final Completion
September 2021
Final Project Closeout
December 2021

The projects are intended to construct a sidewalk along Old Fayetteville Road from Ricefield Branch to Leland Middle School, a multi-use path extension along Village Road from the Brunswick County Senior Center to Sturgeon Creek, and a sidewalk loop from Town Hall Drive down Village and Old Fayetteville Roads. 

AECOM

Engineering and Design

Simmons Public Utility Site Work

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Pedestrian Improvements Project Details
Construction Plans
Pedestrian Improvements Construction Plans
Town Hall Drive
New sidewalks in front of Leland Middle School
New sidewalks along Old Fayetteville Road
New sidewalks along Village Road
New sidewalks along Village Road
Framing for new sidewalks
New sidewalks along Old Fayetteville Road
New sidewalks near Leland Library
Construction to begin on Town Hall Drive

Project Updates

Town Hall Drive Lane Closure
Thursday, September 2, 2021

The contactor will have one lane closed on Tuesday, September 7, 2021 as they adjust the sewer manhole along Town Hall Drive. Work will require one lane to be closed with flagging for the duration. Please use caution when driving on Town Hall Drive. Town Staff and residents will still be able to access Town Hall and Founders Park.

Construction to Begin on Town Hall Drive
Tuesday, August 10, 2021

Construction is slated to begin this week on Town Hall Drive. Work includes widening Town Hall Drive, new sidewalks, improved drainage, a new crosswalk, and on street parking. The contractor will be working off the shoulder for most of the work and will require one lane to be closed with flagging for the duration over the next several weeks. Please use caution when driving on Town Hall Drive. Town Staff and residents will still be able to access Town Hall and Founders Park.

Sidewalk Work Continues
Friday, July 23, 2021

The contractor is finishing up along Old Fayetteville Road near Leland Middle School and will be moving to Town Hall Drive and Village Road to begin moving water meters, installing remaining sidewalks, and paving the Multi-Use Path. Work will continue into the month of August.

New Street Lights
Friday, June 4, 2021

The contractor continues to install concrete sidewalk along Village Road. New streetlights have been installed along Town Hall Drive and the contractor will be installing storm drainpipe along Old Fayetteville Road this month.

Construction Continues
Wednesday, May 5, 2021

The contractor is continuing to lay concrete sidewalk in front of Leland Middle School and down Old Fayetteville Road as well as continuing to clear and grade along Village Road and Town Hall Drive for both the sidewalk and Multi-Use Path.

Leland Middle School Sidewalks
Wednesday, March 24, 2021

The contractor is installing new sidewalks in front of Leland Middle School.

Pages