STP-DA Pedestrian Improvements (U-5534I, J, K)

Milestone timeline

Bid Closing
Completed: Dec 3, 2020
December 2020
Notice to Award
Completed: Dec 18, 2020
December 2020
Notice to Proceed
Completed: Feb 1, 2021
January 2021
Construction Commences
Completed: Feb 8, 2021
February 2021
Substantial Completion
Completed: Dec 13, 2021
December 2021
Final Completion
March 2022
Final Project Closeout
April 2022

The projects are intended to construct a sidewalk along Old Fayetteville Road from Ricefield Branch to Leland Middle School, a multi-use path extension along Village Road from the Brunswick County Senior Center to Sturgeon Creek, and a sidewalk loop from Town Hall Drive down Village and Old Fayetteville Roads. 

AECOM

Engineering and Design

Simmons Public Utility Site Work

Construction Contractor

SEPI Engineering & Construction

Construction Adminstration & Construction Engineering Inspection Services

Documents

Project Information Sheet
Pedestrian Improvements Project Details
Construction Plans
Pedestrian Improvements Construction Plans
Town Hall Drive
New sidewalks in front of Leland Middle School
New sidewalks along Old Fayetteville Road
New sidewalks along Village Road
New sidewalks along Village Road
Framing for new sidewalks
New sidewalks along Old Fayetteville Road
New sidewalks near Leland Library
Construction to begin on Town Hall Drive
Pervious Concrete

Pages

Project Updates

Town Hall Drive Road Closure
Monday, January 24, 2022

Town Hall Drive will be closed today Monday, January 24, 2022 and tomorrow Tuesday, January 25, 2022 for the contractor to mill and place asphalt along Town Hall Drive.  Please use Old Fayetteville Road to access both Town Hall and Founder’s park.  Work will be performed from 10:00 am to 6:00 pm both days and will open to all traffic during the evening hours.  Please use caution when driving in the area.

Town Hall Drive Paving
Thursday, January 20, 2022

Due to the changing weather conditions, the contractor was unable to mill and place asphalt along Town Hall Drive this week.  Town Staff will work with the contractor and engineer on an updated construction schedule. 

Town Hall Drive Closure
Tuesday, January 18, 2022

Town Hall Drive will be closed on Wednesday, January 19, 2022 and Thursday, January 20, 2022 for the contractor to mill and place asphalt along Town Hall Drive.  Please use Old Fayetteville Road to access both Town Hall and Founder’s park.  Work will be performed from 8:00 am to 6:00 pm both days and will open to all traffic during the evening hours.  Please use caution when driving in the area.

Striping Town Hall Drive
Tuesday, December 28, 2021

The contractor will be applying paint to the three crosswalks across Town Hall Drive tomorrow, Wednesday, December 29, 2021.  Work will require the road to be closed for 20-30 minutes at a time while crews install paint.  If closed, please use alternate route off Old Fayetteville Road to access Town Hall and Founder’s Park.

Work at Town Hall Entrance Continues
Tuesday, December 14, 2021

The contractor will be forming up the sidewalk and curb ramp and pouring concrete at the entrance to Town Hall on Wednesday, December 15, 2021.  Work will only require a few hours to complete.  If active construction is going on, please use the entrance off Old Fayetteville Road to enter and exit Town Hall.

Town Hall Entrance Closure
Friday, December 10, 2021

The contractor working on Town Hall Drive will be closing the entrance to Town Hall on Monday, December 13, 2021.  Please use the entrance off Old Fayetteville Road to enter and exit Town Hall.

Pages