Leland Fire Station 51
Milestone timeline

Fire Station 51 will be located at the new Municipal Operations Center Campus at 1987 Andrew Jackson Highway NE. This station will improve the Town's response times to fire and life safety events in the area.
Environments Unlimited, Inc.
Design-Build Contractor
Documents
Project Updates
As we are nearing the start of construction, final construction plans expected within the week. Building materials will begin to arrive in June with a goal of starting sitework in May.
Preliminary Architectural Design and Site Plans have been approved and the Design Builder is working towards 100% construction drawings.
After multiple rounds of both architectural and site plans, we are nearing the completion of preliminary design. Mechanical, electrical, plumbing, and strutural engineers will soon begin working on producing full set building plans.
First round, preliminary design plans were recieved and have been reviewed by the Town. These site plans have been marked up based on discussions, are currently being reviewed by the architecture firm, and a revised plan is expected in June.
Planning for both architectural and site design has commenced and the Town is awaiting the first draft plans to be returned for the initial review.
The Town issued a Notice to Proceed to Environments Unlimited, Inc. and contract documents have been signed. Pre-Construction planning will begin immediately.