Skip to main content

Ocean Gate Plaza Intersection Improvements

Ocean Gate Plaza Intersection Improvements

A project to improve the intersection at Ocean Gate Plaza and New Pointe Boulevard. The scope of the project includes installation of a single-lane teardrop roundabout, stormwater improvements, new sidewalks, pedestrian crosswalks, pavement markings, and street signs. The project will improve the busy commercial intersection, improve safety for motorists and pedestrians alike, and improve pedestrian connectivity and the flow of traffic.

DAVENPORT

Engineering and Design

C.M. Mitchell Construction Company, Inc.

Construction Contractor

Project Updates

Water Shutdown
Thursday, March 19, 2026

H2GO will be shutting down a section of water mainline at the intersection of Ocean Gate Plaza and New Point Boulevard for the contractor to relocate utilities for the Town’s Ocean Gate Plaza Roundabout project. The shutdown will start at 10 p.m. on Tuesday, March 24, 2026, and will be turned back on at 4 a.m. on Wednesday, March 25, 2026.

Rebuild
Wednesday, March 11, 2026

Construction crews have begun work on the full rebuild of the roadway. Next steps are to compact and install ABC Stone.

Curb & Gutter
Monday, March 09, 2026

Curb and gutter is being installed along Ocean Gate Plaza and New Pointe Boulevard. 

Stormwater Improvements
Tuesday, March 03, 2026

Stormwater improvements to include eight new catch basins and storm drainpipes have been installed along Ocean Gate Plaza.

Construction Start
Tuesday, January 27, 2026

Construction has begun on the Ocean Gate Plaza and New Pointe Intersection improvements project. The project is expected to take approximately four months to complete and during this time, the intersection of Ocean Gate Plaza and New Pointe Boulevard will be closed to all traffic.  

Construction to Begin
Tuesday, January 20, 2026

Construction is scheduled to begin on Tuesday, January 27, 2026. The project is expected to take approximately four months to complete and during this time, the intersection of Ocean Gate Plaza and New Pointe Boulevard will be closed.

Notice of Award
Thursday, October 16, 2025

Town Council approved the bid and selection of C.M. Mitchell Construction Company as the construction contractor on the project.

Advertisement for Bids
Tuesday, August 19, 2025

The Town of Leland invites the submission of sealed construction bids for the Town of Leland Ocean Gate Plaza Roundabout project. The bid advertisement provides complete information on the scope of work, how to obtain bidding documents, timelines, and submission requirements, and can be found at https://www.townofleland.com/rfps-rfqs. The Town will receive sealed bids for the construction of the project through Thursday, September 18, 2025, at 3 p.m.

Utility Relocation
Thursday, April 24, 2025

Utility work has begun with relocating the underground utilities to improve the intersection at Ocean Gate Plaza and New Pointe Boulevard.  Crews from Lee Electric will be out on site for the next several months.  Work will take place along the right of way.  Residents should use caution when driving in the area.

Final Plans
Monday, July 01, 2024

The Engineer is updating the Final Plans for the intersection improvements. Completion of the construction design plans is anticipated for Spring/Summer 2025.