Baldwin Drive Improvements

Baldwin Drive Improvements

A project to improve Baldwin Drive from Navassa Road to Lee Drive. The scope of the project includes widening and paving of Baldwin Drive, installing sidewalks, stormwater, and drainage improvements.

WithersRavenel

Engineering and Design

TBD

Construction Contractor

Project Updates

Public Open House
Monday, September 12, 2022

The Town of Leland will be hosting a Public Open House for the Baldwin Drive Improvements project on Thursday, September 22, 2022 at 6 p.m. at Town Hall.  Residents will have a chance to review the planned improvements, ask questions, and get an overview of the upcoming project.

Concept Plans
Tuesday, May 31, 2022

Survey of the project is complete. The engineer is developing the concept plan for Town review.

Survey
Tuesday, April 26, 2022

Survey crews will be out along Baldwin Drive starting Monday, May 2, 2022. Their work will take several weeks to complete. Please use caution when survey crews are working in the area.

Engineer
Tuesday, April 05, 2022

The Town has brought onboard Withers Ravenel to survey, design and bid the Baldwin Drive Improvements project. Survey is expected to begin on May 2, 2022, and will take several weeks to complete. Please use caution when survey crews are out.

Town Project
Tuesday, February 15, 2022

The Town is working to bring an engineering firm on board to begin survey and design this spring.