Town of Leland Streets Resurfacing 2021-2022

Milestone timeline

Design
Completed: May 10, 2022
May 2022
Bid Closing
June 2022
Notice to Award
June 2022
Notice to Proceed
July 2022
Construction Commences
July 2022
Substantial Completion
October 2022
Final Completion
November 2022
Final Project Closeout
December 2022

To resurface 9 streets within the Town limits to include Olde Waterford Way, portion of Woodwind Drive, Palm Ridge Drive, Old Village Circle, Royal Palm Way, portion of Pine Harvest Drive, Bentgreen Drive, West Gate Drive, intersection at New Pointe Blvd, and the commercial section of Grandiflora Drive. The scope of the project includes milling, full depth patches as needed, and asphalt overlay of those 9 streets.

CLD Engineering, LLC

Engineering and Design

TBD

Construction Contractor

Documents

Town of Leland Streets Resurfacing
Proposed Repaving Exhibit Map
Invitation to Bid
Town of Leland Streets Resurfacing 2021-2022
Olde Waterford Way
West Gate Drive
West Gate Drive
Magnolia Greens Commerical Section
Magnolia Greens Commerical Section
Bentgreen Drive
Bentgreen Drive

Project Updates

Project Advertisement
Tuesday, May 10, 2022

Final plans and bid documents are complete.  Project is being advertisement for construction bids.  Bid closing is slated for 2:00 pm on Thursday, June 2, 2022.

Final Design Drawings
Friday, April 22, 2022

Final Construction drawings and bid documents are being finalized by the Engineer and the project will go to Advisement in May.

Preliminary Design Drawings
Monday, March 7, 2022

Preliminary design drawings have been submitted for Town review. Town will review and provide comments back to the engineer.

Survey Update
Tuesday, February 1, 2022

Geotechnical and survey crews will be out on the project starting tomorrow, February 2, 2022 to mark the areas that will require a full depth rebuild and survey the additional streets of Royal Palm Way and Grandiflora Drive.  The survey data for the additional streets will be included in the Preliminary Plans.

Additional Streets Added
Tuesday, December 14, 2021

The Town has added Royal Palm Way and approximately 200 feet on Grandiflora Drive just pass Cumbertree Court to this coming year’s resurfacing project.  The Engineer is working on getting additional survey and Geotechnical Inspection scheduled and will input the data into the Preliminary Plans.

Survey and Geotechnical Inspection Complete
Friday, December 3, 2021

Geotechnical Inspection Phase 2 consisting of 12 cores throughout the projects limits is complete.  The Engineer is compiling Preliminary plans for Town Staff to review.

Pages